Cement Calculator

For site-mixed concrete: enter the wet volume you need and the mix ratio. The calculator applies the dry-volume factor and splits cement, sand and gravel quantities. Bag size is configurable.

Cement Calculator

Concrete & Construction

ft³

Cement bags

7× 50 kg

Sand

15.4 ft³ · 0.436 m³

≈ 2 lb at 1.6 t/m³

Gravel

30.8 ft³ · 0.872 m³

≈ 3 lb at 1.5 t/m³

Dry volume

53.9 ft³ · 1.526 m³

wet 35 ft³ × 1.54

Calculation breakdown

  1. 1Dry volume: 0.991 × 1.54 = 1.526 m³
  2. 2Mix split: 1:2:4 → cement 0.143, sand 0.286, gravel 0.571
  3. 3Cement volume: 0.218 m³ ÷ 0.0347 m³ = 7 bags

Dry volume = Wet volume × 1.54 (voids factor).

Part volume = Dry volume ÷ (C : S : G sum).

Cement bags = Cement volume ÷ bag volume (50 kg bag ≈ 0.0347 m³ · 94 lb bag = 1 ft³).